Stay Updated

Share Stay Updated on Facebook Share Stay Updated on Twitter Share Stay Updated on Linkedin Email Stay Updated link

Please see the News and Notices Page for all City updates.

The City is committed to working with you to understand and utilise your views, concerns, and aspirations, to guide sustainable outcomes in our decision-making processes to strengthen community cohesion, city amenity and the quality of life for the local community.

Our online community engagement hub, Your Voice Nedlands provides you and the community with the opportunity to offer genuine input into a broad range of projects, activities and decisions of Council. The hub also gives us an avenue to communicate decisions and activities.

This page is regularly updated with news such as infrastructure, closures and events.

The City is committed to working with you to understand and utilise your views, concerns, and aspirations, to guide sustainable outcomes in our decision-making processes to strengthen community cohesion, city amenity and the quality of life for the local community.

Our online community engagement hub, Your Voice Nedlands provides you and the community with the opportunity to offer genuine input into a broad range of projects, activities and decisions of Council. The hub also gives us an avenue to communicate decisions and activities.

This page is regularly updated with news such as infrastructure, closures and events.

Please see the News and Notices Page for all City updates.

  • Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works

    Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Facebook Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Twitter Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Linkedin Email Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The City has appointed Civcon Civil to undertake road resurfacing and associated works from Wednesday 5 April 2017. These works will be undertaken between 7.00 am to 5.00 pm, Monday to Friday.

    During the works, road closures will be required with detours provided. Closures are planned to cease around 4.30 pm to minimise inconvenience. However, we do ask that you consider increasing your commuting times during peak periods when planning your journey.

    The operations team on site will endeavour to offer access to your property at all times, however there may be short periods when materials are required to cure. On these occasions the City will ensure contact has been made and suitable alternative arrangements have been discussed.

    The kerbing will be replaced and upgraded with a new standard semi-mountable kerb. Where necessary, the reticulation may be temporarily re-routed to allow the works to proceed.

    If you are a property owner, it is important that you test your reticulation system and report any faults within two weeks of the works being completed. If the reticulation is damaged during the works, the City will make good any repairs. However, after this period the City cannot be held responsible for further repairs.

    The program for the works follow:

    • Site preparation: 5 to 7 April
    • Remove and prepare new kerbing for sealing: 10 to 14 April
    • Remove and reinstate drainage: 14 to 24 April
    • Profile and seal road: 25 to 26 April
    • Install new kerbing and pram ramps: 27 to 28 April
    • Reinstate reticulation: 1 May
    • Asphalting of road: 3 May
    • Reinstatement of driveway crossovers: 4 to 5 May
    • Completion, including site clean-up: 8 May

    For enquiries, please contact Paul Beasley, Engineering Projects Coordinator, telephone (08) 9273 3500, or by email, pbeasley@nedlands.wa.gov.au or the Contractor's Supervisor, Sean Connolly, telephone 0410 402 004.

    Thank you for your cooperation during this period.

  • Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade

    Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Facebook Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Twitter Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Linkedin Email Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade link
    CLOSED: This discussion has concluded.
    supporting image

    The City of Nedlands have been awarded a grant of $461,000 in Federal Blackspot funding to undertake an upgrade of the intersection of Railway Road and Gugeri Street with Loch Street to improve road safety following a high number of crashes in the area.

    The safety issues at the intersection have been recognised by the Australian Government’s Blackspot Program and the funding for the upgrade to the intersection goes a long way to help enhance and improve road safety within the City.

    To find our more, please visit the engagement page.


  • Marlows Wall - Refurbishment

    Share Marlows Wall - Refurbishment on Facebook Share Marlows Wall - Refurbishment on Twitter Share Marlows Wall - Refurbishment on Linkedin Email Marlows Wall - Refurbishment link
    CLOSED: This discussion has concluded.
    supporting image

    Refurbishment works is being undertaken on the wall from late March 2017 for a period of up to four weeks.

    The works will improve the safety, aesthetics and functionality of the wall which separates the John XXIII College from the road reserve and include re-construction (where required), re-mortaring, re-pointing and bracing of the wall. Some sections at the southern end will require re-positioning back from the embankment.

    Please remain clear of the work site whilst the repairs are underway.

    For further information, please contact the Parks Projects Coordinator, Daniel Lewis on (08) 9273 3500 or via email council@nedlands.wa.gov.au


  • College Park Youth Recreation Area - Maintenance of Bicycle Pump Track

    Share College Park Youth Recreation Area - Maintenance of Bicycle Pump Track on Facebook Share College Park Youth Recreation Area - Maintenance of Bicycle Pump Track on Twitter Share College Park Youth Recreation Area - Maintenance of Bicycle Pump Track on Linkedin Email College Park Youth Recreation Area - Maintenance of Bicycle Pump Track link
    CLOSED: This discussion has concluded.
    supporting image

    Maintenance will be undertaken on the Bicycle Pump Track, College Park Youth Recreation Area during March 2017.

    The works include installing drainage and preparing for an asphalt surface. These works are designed to extend the life of the facility, to be more functional following rain events and reduce ongoing maintenance costs.

    It would be appreciated if Park Users refrain from using the track whilst the works are progressing.

    If you would like further information, please contact Daniel Lewis, Parks Projects Coordinator on (08) 9273 3500.

    Thank you for your patience during this time.
  • Pets at the Park 2017

    Share Pets at the Park 2017 on Facebook Share Pets at the Park 2017 on Twitter Share Pets at the Park 2017 on Linkedin Email Pets at the Park 2017 link
    CLOSED: This discussion has concluded.
    supporting image

    Thank you to everyone who attended the 2017 event and for completing the survey. We look forward to the 2018 event.

  • Boronia Avenue (from 45 Boronia Avenue to Stirling Highway)

    Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Facebook Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Twitter Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Linkedin Email Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.

  • Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification

    Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Facebook Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Twitter Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Linkedin Email Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification link
    CLOSED: This discussion has concluded.
    supporting image

    The City of Nedlands and the Town of Cambridge have been awarded a Road Rehabilitation Grant for $580,000 from the Metropolitan Regional Road Group to upgrade the intersection at Brockway Road, Brookdale Street and Underwood Avenue.

    To find out more, please visit the engagement page.


  • Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated

    Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Facebook Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Twitter Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Linkedin Email Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.



  • Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works

    Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Facebook Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Twitter Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Linkedin Email Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.

  • Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works

    Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Facebook Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Twitter Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Linkedin Email Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.