Stay Updated

Share Stay Updated on Facebook Share Stay Updated on Twitter Share Stay Updated on Linkedin Email Stay Updated link

Please see the News and Notices Page for all City updates.

The City is committed to working with you to understand and utilise your views, concerns, and aspirations, to guide sustainable outcomes in our decision-making processes to strengthen community cohesion, city amenity and the quality of life for the local community.

Our online community engagement hub, Your Voice Nedlands provides you and the community with the opportunity to offer genuine input into a broad range of projects, activities and decisions of Council. The hub also gives us an avenue to communicate decisions and activities.

This page is regularly updated with news such as infrastructure, closures and events.

The City is committed to working with you to understand and utilise your views, concerns, and aspirations, to guide sustainable outcomes in our decision-making processes to strengthen community cohesion, city amenity and the quality of life for the local community.

Our online community engagement hub, Your Voice Nedlands provides you and the community with the opportunity to offer genuine input into a broad range of projects, activities and decisions of Council. The hub also gives us an avenue to communicate decisions and activities.

This page is regularly updated with news such as infrastructure, closures and events.

Please see the News and Notices Page for all City updates.

Category Parking Roads and Traffic   Show all

  • Nagal Pass, Stubb Terrace - Roundabout reconstruction

    Share Nagal Pass, Stubb Terrace - Roundabout reconstruction on Facebook Share Nagal Pass, Stubb Terrace - Roundabout reconstruction on Twitter Share Nagal Pass, Stubb Terrace - Roundabout reconstruction on Linkedin Email Nagal Pass, Stubb Terrace - Roundabout reconstruction link
    CLOSED: This discussion has concluded.
    supporting image

    The City has appointed Civcon Civil to undertake the reconstruction of the roundabout at Nagal Pass, Stubbs Terrace.

    This work will be undertaken on the weekend of 27-28 May, with work commencing on Friday 26 May 2017. The hours of work will be undertaken between 9.00 am to 6.00 pm on Friday, and 7.00 am to 6.00 pm Saturday. Curing of the concrete will occur during Saturday night and Sunday.

    The road will be closed from 9.00 am on Friday through to early Sunday evening. The closure will enable the demolition, construction and curing of the new roundabout to be undertaken in a safe and efficient manner.

    During the closure, traffic controllers will be on-site during the day and late into the night to provide advice on the diversion route as required.

    If you have questions or concerns in relation to this project, please contact the City's Project Manager (Paul Beasley), telephone 0406 376 256.

    For onsite issues, please contact Civcon Civil's Project Manager, Sean Connolly, telephone 0410 402 004.

  • Street Signage Upgrades

    Share Street Signage Upgrades on Facebook Share Street Signage Upgrades on Twitter Share Street Signage Upgrades on Linkedin Email Street Signage Upgrades link
    CLOSED: This discussion has concluded.
    supporting image

    Street signage is being upgraded across the City over the next 6 months. This program is undertaken as part of the City’s maintenance programs to improve the visibility of the signage as well as providing consistency in design standards.

    Areas of Mt Claremont are a focus as there is still signage that was installed by the Developer which has either faded or sustained damage making it difficult to see and read.


    The program of works is as follows:

    • Floreat: Completed
    • Mt Claremont (Between Stephenson and Mooro Drive): Currently underway
    • Mt Claremont (Between Mooro Drive and Alfred Road/Brockway): May 2017
    • Mt Claremont (Between Cottesloe Golf Course and Mooro Avenue): June 2017
    • Mt Claremont (St Peter’s Square): July 2017

    During the upgrade process, there will be some instances due to visibility issues where existing poles may need to be relocated or replaced. However in most circumstances the only change will be the replacement of the sign blade itself.

    The street sign blade will look like:

  • Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works

    Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Facebook Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Twitter Share Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works on Linkedin Email Kitchener Street (Verdun Street to Aberdare Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The City has appointed Civcon Civil to undertake road resurfacing and associated works from Wednesday 5 April 2017. These works will be undertaken between 7.00 am to 5.00 pm, Monday to Friday.

    During the works, road closures will be required with detours provided. Closures are planned to cease around 4.30 pm to minimise inconvenience. However, we do ask that you consider increasing your commuting times during peak periods when planning your journey.

    The operations team on site will endeavour to offer access to your property at all times, however there may be short periods when materials are required to cure. On these occasions the City will ensure contact has been made and suitable alternative arrangements have been discussed.

    The kerbing will be replaced and upgraded with a new standard semi-mountable kerb. Where necessary, the reticulation may be temporarily re-routed to allow the works to proceed.

    If you are a property owner, it is important that you test your reticulation system and report any faults within two weeks of the works being completed. If the reticulation is damaged during the works, the City will make good any repairs. However, after this period the City cannot be held responsible for further repairs.

    The program for the works follow:

    • Site preparation: 5 to 7 April
    • Remove and prepare new kerbing for sealing: 10 to 14 April
    • Remove and reinstate drainage: 14 to 24 April
    • Profile and seal road: 25 to 26 April
    • Install new kerbing and pram ramps: 27 to 28 April
    • Reinstate reticulation: 1 May
    • Asphalting of road: 3 May
    • Reinstatement of driveway crossovers: 4 to 5 May
    • Completion, including site clean-up: 8 May

    For enquiries, please contact Paul Beasley, Engineering Projects Coordinator, telephone (08) 9273 3500, or by email, pbeasley@nedlands.wa.gov.au or the Contractor's Supervisor, Sean Connolly, telephone 0410 402 004.

    Thank you for your cooperation during this period.

  • Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade

    Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Facebook Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Twitter Share Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade on Linkedin Email Railway Road, Gugeri Street Intersection with Loch Street Intersection Upgrade link
    CLOSED: This discussion has concluded.
    supporting image

    The City of Nedlands have been awarded a grant of $461,000 in Federal Blackspot funding to undertake an upgrade of the intersection of Railway Road and Gugeri Street with Loch Street to improve road safety following a high number of crashes in the area.

    The safety issues at the intersection have been recognised by the Australian Government’s Blackspot Program and the funding for the upgrade to the intersection goes a long way to help enhance and improve road safety within the City.

    To find our more, please visit the engagement page.


  • Marlows Wall - Refurbishment

    Share Marlows Wall - Refurbishment on Facebook Share Marlows Wall - Refurbishment on Twitter Share Marlows Wall - Refurbishment on Linkedin Email Marlows Wall - Refurbishment link
    CLOSED: This discussion has concluded.
    supporting image

    Refurbishment works is being undertaken on the wall from late March 2017 for a period of up to four weeks.

    The works will improve the safety, aesthetics and functionality of the wall which separates the John XXIII College from the road reserve and include re-construction (where required), re-mortaring, re-pointing and bracing of the wall. Some sections at the southern end will require re-positioning back from the embankment.

    Please remain clear of the work site whilst the repairs are underway.

    For further information, please contact the Parks Projects Coordinator, Daniel Lewis on (08) 9273 3500 or via email council@nedlands.wa.gov.au


  • Boronia Avenue (from 45 Boronia Avenue to Stirling Highway)

    Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Facebook Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Twitter Share Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) on Linkedin Email Boronia Avenue (from 45 Boronia Avenue to Stirling Highway) link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.

  • Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification

    Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Facebook Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Twitter Share Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification on Linkedin Email Brockway Road, Brookdale Street and Underwood Avenue Intersection Modification link
    CLOSED: This discussion has concluded.
    supporting image

    The City of Nedlands and the Town of Cambridge have been awarded a Road Rehabilitation Grant for $580,000 from the Metropolitan Regional Road Group to upgrade the intersection at Brockway Road, Brookdale Street and Underwood Avenue.

    To find out more, please visit the engagement page.


  • Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated

    Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Facebook Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Twitter Share Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated on Linkedin Email Loftus Street (between Carrington Street and Government Road - Road Resurfacing and Associated link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.



  • Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works

    Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Facebook Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Twitter Share Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works on Linkedin Email Asquith Street (between Mayfair Street and Rochdale Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.

  • Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works

    Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Facebook Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Twitter Share Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Linkedin Email Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works link
    CLOSED: This discussion has concluded.
    supporting image

    The road resurfacing and associated works have now been completed. The works included asphalting, sealing, and installing kerbs, pram ramps and concrete aprons.

    Thank you for your patience during this time.