Share Works program on Facebook
Share Works program on Linkedin
Email Works program link
Stage 2 of Safe Active Streets is progressing well with the following timeline expected:
- Sector 1: Dalkeith to Vincent - COMPLETE
- Sector 2: Vincent to Taylor - Start date 14 Sep 2020, expected completion 20 October 2020
- Sector 3: Taylor to Rockton - expected start date 16 October 2020, expected completion 24 November 2020
Further updates will be posted to this page.
Share Re-commencement of Work on Jenkins Avenue, Nedlands on Facebook
Share Re-commencement of Work on Jenkins Avenue, Nedlands on Linkedin
Email Re-commencement of Work on Jenkins Avenue, Nedlands link
The City apologises for the previous delay in delivering Stage 2 of the Safe Active Streets project and we appreciate the community's patience.
WCP Civil will be recommencing the works from Monday, 10 August 2020. The work will commence from Dalkeith Road and continue along Jenkins Avenue for a period of three months until completion. However, this will be dependent on the weather and resources.
The delay in completing this work was impacted by COVID-19, but also due to an audit of Stage 1, commissioned by the City to identify any changes that could be implemented based on reviewing the Elizabeth Street portion of work. The audit identified an opportunity to improve the design along Jenkins Avenue based on this audit, whilst acknowledging the need to maintain the project within the existing budget.
The key changes involve:
- Removal of the raised plateaus through the intersection with the exception of the one at Dalketh Road
- Installation of road humps adjacent to tree nibs approximately mid-way between intersections
- Reduce the gradient on the Dalkeith Road plateau.
The changes have been approved by the Department of Transport and Main Roads WA, The modifications are expected to improve cyclist safety by providing a gentler slope and an option to bypass the road humps if desired.
The new design is available to view in the document library. Images of how these road humps look on road surfaces can be viewed in the Photo Library.
Share Further Delay in Recommencing Project on Facebook
Share Further Delay in Recommencing Project on Linkedin
Email Further Delay in Recommencing Project link
Unfortunately the work scheduled to recommence on the 22 June 2020 has been deferred.
The City apologises to the community for the unforeseen delays in enabling this work to be completed as originally planned.
We are currently in neogiations with the contractor to discuss when this work will be rescheduled and the new expected timelines for completion. Being Winter, this work could still see further delays due to bad weather.
In the interim, the City is taking immediate action to improve the onsite temporary traffic management and remove excess soil currently stored on the verge.
Share Jenkins Avenue Road Upgrades - Recommencement of Works on Facebook
Share Jenkins Avenue Road Upgrades - Recommencement of Works on Linkedin
Email Jenkins Avenue Road Upgrades - Recommencement of Works link
WCP Civil will be re-starting the Jenkins Avenue road upgrades on behalf of the City of Nedlands.
Road re-surfacing and associated works will recommence from Dalkeith Rd on the 22 June 2020 and continue along Jenkins Avenue for a period of 3 months until completion however this will be dependent on the weather and resources.
The works will include:
- Road / intersection alterations
- New drainage
- Profiling of existing road
- New kerb
- Footpath accommodation works
- Asphalt surfacing
Works will be undertaken during weekdays between the hours of 7:00am - 6:00pm. Some preparatory works may need to be undertaken outside of these times and dates.
Road closures will be installed with detours positions around the work site. Local traffic will continue to have access whilst the closures are in place. On site traffic controllers will aid as required.
If you have any enquiries relating to the staging of the works or access to your property, please contact the WCP Civil Site Supervisor Michael Flower on 0448 270 629 or WCP Civil Project Manager Shaun Lynch 0455 909 689.
Share Stage 2 construction on hold on Facebook
Share Stage 2 construction on hold on Linkedin
Email Stage 2 construction on hold link
The City of Nedlands advise that due to Government Restrictions regarding COVID-19, Stage 2 of the Safe Active Streets project Jenkins Ave is momentarily on hold for approximately 4 weeks. Further updates will be posted via Newsfeed when a re-mobilisation date has been confirmed.
Share Stage 2 to begin construction 9 March 2020 on Facebook
Share Stage 2 to begin construction 9 March 2020 on Linkedin
Email Stage 2 to begin construction 9 March 2020 link
The City is progressing with the construction of the long awaited Safe Active Street for Elizabeth Street and Jenkins Avenue. The first stage of the project is almost complete, and Stage 2 (Jenkins Avenue, from Dalkeith Road to Bay Road) will be commencing on Monday 9 March 2020. The project will be constructed by WCP Civil on behalf of the City of Nedlands.
Road re-surfacing and associated works will commence at the Dalkeith Road end of Jenkins Avenue and continue along Jenkins Avenue for a period of approximately 4 months until completion, however this will be dependent on the weather and resources.
WCP Civil will be undertaking the construction work in a staged process, completing three blocks at a time. Works will be undertaken between Monday to Friday, during the hours of 7:00am and 6:00pm. Road closures will be in place for the works with detours around the work site, however local traffic will continue to have access whilst closures are in place.
Due to the complexity of these works, WCP Civil will be updating all directly affected residents on the progress of the works each fortnight and providing information on any road closures and detours where applicable.
Please ensure that you test your reticulation system and report any faults to the City within two weeks of the works being completed. After this period the City cannot be held responsible for repairs.
You can view the design and traffic management plan via the document library.
Should you have further enquiries, please contact the WCP Site Supervisor Michael Flower on 0448 270 629 or WCP Project Manager Shaun Lynch on 0455 909 689. Alternatively, you can contact the City's representative, Paul Beasley on (08) 9273 3500.
Share Elizabeth Street/Bruce Street Roundabout - Road Resurfacing on Facebook
Share Elizabeth Street/Bruce Street Roundabout - Road Resurfacing on Linkedin
Email Elizabeth Street/Bruce Street Roundabout - Road Resurfacing link
WCP Civil will be carrying out road re-surfacing works on behalf of the City at the Elizabeth street/Bruce Street roundabout.
The re-surfacing will commence on Monday 17 February between the hours of 7:00am - 6:00pm, for a period of 2 days to lower the newly constructed speed humps.
Road closures will be installed with detours positioned around the work site. Local traffic will continue to have access whilst the closures are in place, on-site traffic controllers will aid as required.
Should you have any further enquiries, please contact the WCP Site Supervisor Michael Flower on
0448 270 629 or WCP Project Manager Shaun Lynch 0455 909 689.
Further updates will be posted to this page.
Share Updated Drawings on Facebook
Share Updated Drawings on Linkedin
Email Updated Drawings link
There are updated drawings available for viewing in the document library.
Works progressed from Broadway to Archdeacon Street this week with new asphalt to be laid within the coming weeks. Western Power have confirmed they will relocate the street light outside the Broadway Fair Shopping Centre on Wednesday 6 November.
Share Update - Stage 1: Elizabeth Street on Facebook
Share Update - Stage 1: Elizabeth Street on Linkedin
Email Update - Stage 1: Elizabeth Street link
Construction is progressing well with Stage 1 of our Safe Active Street Program and is on track to progress further up from the Broadway end of Elizabeth Street shortly.
You can see current photos of the works, here.
Further updates will be posted to this page.
Share Construction commenced - Safe Active Streets Stage One on Facebook
Share Construction commenced - Safe Active Streets Stage One on Linkedin
Email Construction commenced - Safe Active Streets Stage One link
The first stage of construction of the Nedlands Safe Active Streets program has now commenced. Construction began on 9 September on the Broadway end of Elizabeth Street and is scheduled for completion before Christmas.
This collaborative project between the City & the Department of Transport will create a safe thoroughfare for pedestrians, cyclists and motorists with the focus of the design based around safety and residential amenity.
Further updates will be posted to this page.