Re-commencement of Work on Jenkins Avenue, Nedlands

The City apologises for the previous delay in delivering Stage 2 of the Safe Active Streets project and we appreciate the community's patience.

WCP Civil will be recommencing the works from Monday, 10 August 2020. The work will commence from Dalkeith Road and continue along Jenkins Avenue for a period of three months until completion. However, this will be dependent on the weather and resources.

The delay in completing this work was impacted by COVID-19, but also due to an audit of Stage 1, commissioned by the City to identify any changes that could be implemented based on reviewing the Elizabeth Street portion of work. The audit identified an opportunity to improve the design along Jenkins Avenue based on this audit, whilst acknowledging the need to maintain the project within the existing budget.

The key changes involve:

  • Removal of the raised plateaus through the intersection with the exception of the one at Dalketh Road
  • Installation of road humps adjacent to tree nibs approximately mid-way between intersections
  • Reduce the gradient on the Dalkeith Road plateau.

The changes have been approved by the Department of Transport and Main Roads WA, The modifications are expected to improve cyclist safety by providing a gentler slope and an option to bypass the road humps if desired.

The new design is available to view in the document library. Images of how these road humps look on road surfaces can be viewed in the Photo Library.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Works have now concluded.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>