Works program

Stage 2 of Safe Active Streets is progressing well with the following timeline expected:

  • Sector 1: Dalkeith to Vincent - COMPLETE
  • Sector 2: Vincent to Taylor - Start date 14 Sep 2020, expected completion 20 October 2020
  • Sector 3: Taylor to Rockton - expected start date 16 October 2020, expected completion 24 November 2020

Further updates will be posted to this page.


Share Works program on Facebook Share Works program on Twitter Share Works program on Linkedin Email Works program link

Works have now concluded.