Works program
Stage 2 of Safe Active Streets is progressing well with the following timeline expected:
- Sector 1: Dalkeith to Vincent - COMPLETE
- Sector 2: Vincent to Taylor - Start date 14 Sep 2020, expected completion 20 October 2020
- Sector 3: Taylor to Rockton - expected start date 16 October 2020, expected completion 24 November 2020
Further updates will be posted to this page.
Share Works program on Facebook
Share Works program on Twitter
Share Works program on Linkedin
Email Works program link
Works have now concluded.