Share on Facebook
Share on Linkedin
Email this link
The City completed the roundabout works which included the following scope of works:
- Clearing, topsoil strip and removal of vegetation
- Construction of earth works from cut to fill
- Import, place and compact fill
- Box out of new pavement
- Installation of Drainage pipe and pits
- Limestone sub base and base course pavement layers
- New Sealing, kerbing, footpath and Asphalt.
In the next few weeks Main Roads WA will be undertaking the line marking.
Thank you for your patience during this period.
Share on Facebook
Share on Linkedin
Email this link
Please be advised due to the deterioration of the pavement surface, the City has installed a temporary lane closure on the south-west bound lane of Railway Rd at its junction with Gugeri Street.
The closure will remain in place for the remainder of the day and overnight, arrangements have been made for the area to be resurfaced Saturday 8 July, from 7 am onwards.
Thank you for your patience whilst this work is progressing.
Share on Facebook
Share on Linkedin
Email this link
The City has appointed WCP Civil Pty Ltd to undertake the roundabout works. These works will commence on Thursday, 25 May 2017 for a period of approximately five (5) weeks.
The scope of works for this project includes the following activities:
- Clearing, topsoil strip and removal of vegetation
- Construction of earth works from cut to fill
- Import, place and compact fill
- Box out of new pavement
- Installation of Drainage pipe and pits
- Limestone sub base and base course pavement layers
- New Sealing, kerbing, footpath and Asphalt.
During this period private vehicles, pedestrians cannot enter or exit the site during the road modifications for safety reasons.
Any concerns or queries regarding this project please contact the City's Project Manager (Robbie Black), on (08) 9273 3500, email
rblack@nedlands.wa.gov.au.
Share on Facebook
Share on Linkedin
Email this link
The tender for this project was approved by the Council at its meeting on 28 March 2017.
The City is now seeking a Traffic undertaking of the works from the successful tenderer to enable works to commence.
Following receipt and approval of these documents, construction will commence which is expected to be completed by 30 June 2017.
Further updates will be provided as the project progresses.
Share on Facebook
Share on Linkedin
Email this link
The City has progressed with the new design for the upgrade of the intersection of Railway Road and Gugeri Street with Loch Street to improve road safety following a high number of crashes in the area.
This design has been developed with the assistance of the Town of Claremont, businesses and stakeholders within the project area to ensure the design meets the needs of increasing road and pedestrian safety at the intersection and the area more generally. The improvements will include median island widenings, lane realignments, installation of pedestrian traffic lights, lighting, kerbs and drainage, and upgrades to the footpath.
Currently tenders are being called from suitable organisations to undertake the modifications.
This project is being funded through the Australian Government's Blackspot Program to the value of $461,000.