31 August → 01 October 2018
Community Engagement Period
October → November 2018
Reporting to Council on the results and recommendation
November → December 2018
Feedback on outcomes to community and businesses
January 2019
Final design completed
February → April 2019
Scheduling of works, contracts, traffic management plans etc
May → June 2019
Actual construction period