Stirling Highway: footpath upgrades - update on progress
CLOSED: This discussion has concluded.
This program has been updated to reflect the recent approval from Main Roads WA permitting work from 8-2pm on the sections from Bruce Street to Thomas Street.
This approval has enabled the City to condense the program by approximately three weeks with a new revised completion date of 20 March 2019.
The revised construction program is as follows:
- Meriwa Street to Clifton Street: completed
- Baird Avenue to Boronia Street: completion on 10 February
- Mountjoy Road to Florence Street: completion on 10 February
- Bruce Street to Thomas Street: completion on 6 February for night works and 1 March for day works
Further updates will be provided on this page.
Share Stirling Highway: footpath upgrades - update on progress on Facebook
Share Stirling Highway: footpath upgrades - update on progress on Twitter
Share Stirling Highway: footpath upgrades - update on progress on Linkedin
Email Stirling Highway: footpath upgrades - update on progress link
Please see the News and Notices Page for all City updates.