Riverview Court, Dalkeith - Road surface upgrade and associated works

CLOSED: This project has been completed.

The City has contracted the organisation Roads 2000 to undertake road re-surfacing and associated works from Monday 6 August, 2018 for a period of up to five weeks, weekdays from 7am to 5pm.

Site preparation work will be undertaken prior to 6 August.

The project will include drainage and kerb improvements along with the installation of a new road surface.


The timetable is expected to be:

  • Drainage: 6-24 August
  • Profiling and new asphalt – 30 August to 6 September
  • Installing new Kerb – 31 August

Road closures will be required to be in place with detours in place to enable safe movement around the work site. Local traffic will continue to have access.

Traffic Controllers will be present during these times to assist with the safe movement of motorists and pedestrians through the work site.

For operational enquiries, please contact the Contractor's Site Supervisor, Cameron McMeeken on
0437 932 746.


For all other enquiries, please contact the City's Project Manager Myles Bovell on (08) 9273 3500 or email council@nedlands.wa.gov.au.

Thank you for your patience while this work is being undertaken.


Categories: Parking Roads and Traffic
Share Riverview Court, Dalkeith - Road surface upgrade and associated works on Facebook Share Riverview Court, Dalkeith - Road surface upgrade and associated works on Twitter Share Riverview Court, Dalkeith - Road surface upgrade and associated works on Linkedin Email Riverview Court, Dalkeith - Road surface upgrade and associated works link

Please see the News and Notices Page for all City updates.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>