Iris Avenue (between Beatrice Road and Birdwood Parade) - road resurfacing and associated works

CLOSED: This discussion has concluded.

The City has contracted, Roads2000 to undertake road resurfacing and associated works on Iris Avenue between Beatrice Road and Birdwood Parade. The works are scheduled to commence from Monday, 2 October for a period of up to six weeks. The works will include:
  • Preparatory works (including kerb removal, capping of reticulation, installation of signage: 2-4 October
  • Installation of new drainage pits and profiling of the street: 9-10 October
  • Primer sealing: 10-11 October
  • Installing new semi-mountable kerbing installation: 11-12 October
  • Removal and reinstatement of crossover aprons to properties: 13-16 October
  • Asphalt installation: 17-19 October
  • Reticulation repairs: 18-19 October
  • Finishing works: 23-24 October

Access and Road Closures

Road closures will be in place with detours around the work site. Local traffic will continue to have access whilst closures are in place. There will be on-site traffic controllers who will be happy to assist whilst the works are being undertaken.

There will be periods of time (approximately 4 hours) following the laying of new asphalt road surface where vehicle access cannot be permitted. The laying of new asphalt requires a drying time to ensure bitumen doesn't stain property accesses.

Reticulation

It may be necessary to temporarily re-route verge reticulation. The City will repair any reticulation if damaged during the works.

Residents, please ensure that you test your reticulation system and report any faults to City of Nedlands within two weeks of the works being completed. After this period the City of Nedlands cannot be held responsible for repairs.

Contacts

If you have an issue or query in relation to the on-ground works, please contact the Roads2000 Project Manager, James Beier, mobile 0403 546 211 or telephone (08) 9202 0800.

If you have any queries or comments please contact the City's Project Manager, Tim Hollow, telephone (08) 9273 3500.

Thank you for your patience whilst these works are being undertaken.

Categories: Parking Roads and Traffic
Share Iris Avenue (between Beatrice Road and Birdwood Parade) - road resurfacing and associated works on Facebook Share Iris Avenue (between Beatrice Road and Birdwood Parade) - road resurfacing and associated works on Twitter Share Iris Avenue (between Beatrice Road and Birdwood Parade) - road resurfacing and associated works on Linkedin Email Iris Avenue (between Beatrice Road and Birdwood Parade) - road resurfacing and associated works link

Please see the News and Notices Page for all City updates.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>