Alfred Road (between Brockway Road and Mimosa Avenue): Road rehabilitation project - Town of Claremont

CLOSED: This project has concluded.

The Town of Claremont will be undertaking road rehabilitation works in the above section of Alfred Road from Monday, 8 April 2019 for a period of approximately four weeks.

The proposed works will be undertaken as follows:

  • Week 1: remove existing kerb (where applicable), cut and remove some crossover entries and undertake drainage improvements.
  • Week 2: remove existing road surface and install kerbs including in front of crossovers.
  • Week 3: lay road surface and commence reinstatement of crossovers.
  • Week 4: continue reinstatement of crossovers, backfill kerbs, clean up and repair reticulation.

Please note:

  • Some crossovers will need to be modified by the Contractor.
  • Access to properties will be maintained which may include alternative arrangements when the crossovers are being reinstated.
  • Cones will be placed on the work site to ensure all freshly laid concrete or new asphalt can harden for at least up to 24 hours without damage.
  • Access to Alfred Road will be limited during construction periods. However detours and traffic management will be in place to assist motorists and pedestrians.

Please refer to the document library on this page for the notification and Information Sheet provided by the Town of Claremont.

For enquiries, please contact The Town of Claremont's Supervisor of Works, Svetlana Ostrovsky on 9285 4300.
Categories: Parking Roads and Traffic
Share Alfred Road (between Brockway Road and Mimosa Avenue): Road rehabilitation project - Town of Claremont on Facebook Share Alfred Road (between Brockway Road and Mimosa Avenue): Road rehabilitation project - Town of Claremont on Twitter Share Alfred Road (between Brockway Road and Mimosa Avenue): Road rehabilitation project - Town of Claremont on Linkedin Email Alfred Road (between Brockway Road and Mimosa Avenue): Road rehabilitation project - Town of Claremont link

Please see the News and Notices Page for all City updates.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>