29 April → 24 May 2019
Roundabout construction period
29 April → 24 May 2019
Smyth Road - Closure (no access)
01 May → 30 June 2018
Final design work being progressed
09 April → 13 April 2018
If proposal supported, works programmed
02 April → 06 April 2018
Advise to Council on outcomes of engagement
26 February → 19 March 2018
Community Engagement Period