Laneway Auditing Project

Share Laneway Auditing Project on Facebook Share Laneway Auditing Project on Twitter Share Laneway Auditing Project on Linkedin Email Laneway Auditing Project link

The audit is being conducted to support a comprehensive review of the City's asset records, with the aim understanding their specifications and condition. This assessment will be done by City staff, in collaboration with a nominated consultant, who will provide on-site assessment of all laneways within the City. 

Laneway measuring and photographic documentation are expected to commence towards the end of November 2025, with the initial audit report anticipated to be presented to Council in early to mid-2026. 

Following completion of the audit, the City will undertake a series of community presentations, briefings for elected members, and broader public consultation. Feedback gathered during this stage will help guide the City’s decisions on the future of each laneway. A community information session will be held by the City, likely in the first half of 2026. 

Once consultation is complete, further work will be carried out to implement the outcomes of the audit. The overall project expected to be finalised by the end of 2027. 

Additional consultation materials will be distributed upon initial completion of the audit stage, inviting your comments and feedback. 

This page is open to all residents of the City of Nedlands for their information; however, the project will mostly impact those with properties directly abutting a laneway.

PROJECT TIMELINE

Phase One

  • Notification to Impacted Landowners – November 2025

  • Auditing of Laneways Commencing – December 2025 onwards

  • Consideration of Initial Audit Findings – early 2026

  • Council Report for Consent to Advertise Audit Findings – May/June 2026

  • Community Consultation on Laneway Audit – May/June 2026

  • Consultation Concludes – June/July 2026

  • Formal Consideration of Audit Report by Council – July/August 2026

Phase 2 TO FOLLOW – late 2026

The audit is being conducted to support a comprehensive review of the City's asset records, with the aim understanding their specifications and condition. This assessment will be done by City staff, in collaboration with a nominated consultant, who will provide on-site assessment of all laneways within the City. 

Laneway measuring and photographic documentation are expected to commence towards the end of November 2025, with the initial audit report anticipated to be presented to Council in early to mid-2026. 

Following completion of the audit, the City will undertake a series of community presentations, briefings for elected members, and broader public consultation. Feedback gathered during this stage will help guide the City’s decisions on the future of each laneway. A community information session will be held by the City, likely in the first half of 2026. 

Once consultation is complete, further work will be carried out to implement the outcomes of the audit. The overall project expected to be finalised by the end of 2027. 

Additional consultation materials will be distributed upon initial completion of the audit stage, inviting your comments and feedback. 

This page is open to all residents of the City of Nedlands for their information; however, the project will mostly impact those with properties directly abutting a laneway.

PROJECT TIMELINE

Phase One

  • Notification to Impacted Landowners – November 2025

  • Auditing of Laneways Commencing – December 2025 onwards

  • Consideration of Initial Audit Findings – early 2026

  • Council Report for Consent to Advertise Audit Findings – May/June 2026

  • Community Consultation on Laneway Audit – May/June 2026

  • Consultation Concludes – June/July 2026

  • Formal Consideration of Audit Report by Council – July/August 2026

Phase 2 TO FOLLOW – late 2026

Page published: 21 Nov 2025, 09:04 AM