Stage 1 to commence 8 June 2020

As noted above, Stage 1 works will commence 8 June 2020, with Stage 2 expected to begin 17 June 2020.
Stage 1 involves:

  • Demolition of current kerbs, pram ramps, roundabout and road pavement.
  • Construction of new curbs, pram ramps and roundabout.

These works will only be carried out between the hours of 7pm-5am.
For more information regarding site locations, detours and other documentation, head to the document library.

Share Stage 1 to commence 8 June 2020 on Facebook Share Stage 1 to commence 8 June 2020 on Twitter Share Stage 1 to commence 8 June 2020 on Linkedin Email Stage 1 to commence 8 June 2020 link

The works are now complete.