- A seven storey mixed-use building including basement parking garage (car stackers)
- 16 apartments
- 1 commercial tenancy (office)
What is a Development Application (DA)?
Development Application (DA) is an application made to Council seeking consent to carry out development including construction, demolition, change of use, display of advertising, subdivision, or making alterations or additions to a property or premises. A DA is required so that Council can assess the likely impacts of the proposal.
Where is this development located?
The development is located at 135 Broadway, Nedlands.
What is proposed?
The application proposes an amendment to a Mixed Use Development comprising:
Why has the City allowed this application to be proposed?
The City cannot refuse to accept an application for assessment. The City must follow the correct assessment process and will access the application according to the planning process, make a recommendation with the final decision made by the Metro Inner Development Assessment Panel.
What is the City’s view of this application – will it be supported?
The City follows a process for each Development Application received. The application must be assessed according to the provisions of the City's Local Planning Scheme, advice will be sought on design quality and the consultation submissions will be considered prior to the City forming a view on this application.
A recommendation is then presented to the Metro Inner Development Assessment Panel (DAP), who is the final decision maker. The Council have the opportunity to consider the recommendation made to the DAP, but not alter it.
How long would any approval be valid for?
If approved, the planning approval will be valid for an additional 2 years (2026), unless a different period of time is explicitly set.
If the application is refused, what happens next?
If refused, the applicant has a right of appeal by the State Administrative Tribunal in accordance with Part 14 of the Planning and Development Act 2005.
How can I make a submission or be heard by the Council or the Development Assessment Panel (DAP) on this matter?
Submissions can be made via the submission form on this page.
Should you make a submission on the application, you will be notified of the relevant Development Assessment Panel (DAP) meeting and how to apply to make a deputation at the meeting.
Planning
What is the zone for the site?
The site is zoned 'Mixed Use' under the City of Nedlands Local Planning Scheme No.3.
What is proposed land use for this development?
The proposed land use will be Mixed Use, comprising Residential (‘Multiple Dwellings’) and ‘Office’ land uses.
Are there any other provisions that apply to this site?
The application will be assessed against the relevant provisions of the City’s Local Planning Policies, as well as the City's Waste Management Local Planning Policy.
Building Height
What is the building height?
The height of building is 23.6m and comprises seven storeys as viewed from Broadway.
Traffic & Parking
- 26 car bays for residential use; and
- 4 visitor car bays.
How many parking bays are proposed?
A total of 30 car parking bays are proposed which are broken down as follows:
Other Matters
Can the sewerage mains in the area support all the extra residents?
Sewerage and water capacity is controlled by Water Corporation. The Corporation manages impacts of new development on its infrastructure in a number of ways. This includes being a party to the state infrastructure committee, which identifies areas where increased development will take place. This allows for new development to be planned for with any new infrastructure required identified and contributed to by the developer or developers that trigger the upgrade. Water Corporation are also required to make comment on developments of this type.
How will waste be managed?
The application includes a previously approved Waste Management Plan. The alterations to the development are not proposed to change this management plan.
- The applicant submits a Development Application (DA) to the City of Nedlands
- DA is recorded and an initial assessment is made by a City planning officer
- City officer forwards information to the Development Assessment Panel (DAP) at the WA Department for Planning for lodgement
- The City then has 90 days to complete a full submission called a Responsible Authority Report (RAR) to present to the DAP
- CONSULTATION: The DA is advertised according to the City's Consultaton of Planning Proposal Local Planning Policy received by the City are collated, summarised and considered by the City planing officer according to the criteria and planning guidelines/schemes
- REFERRALS: The DA is referered to internal relevant departments within the City for review and comment
- The DA is referred to Main Roads Western Australia (MRWA) for comment, as the proposal abuts Stirling Highway (identified as a Primary Regional Road). Further information or amendments may be requested of the applicant as part of the referrals process.
- The City's planning officer conducts an assesment of the proposal against any relevant development controls and legislation applicable to the DA
- Further information and/or amended plans may be requested of the applicant following assessment
- Following the submission of the RAR, the Development Assessment Panel (DAP) secretariat will organise a meeting time and place for the determination and the applicant and any submitters are made aware as they are welcome to attend the meeting and provide deputations if desired
- The DAP members (consisting of a Chairperson, two independent appropriate professionals - usually architects or planners and two representative City Elected Members) consider the proposal, responsible authority report and any deputations before providing their determination of the application
- The decision is made for or against the application (with conditions and reasoning stated) by the DAP and the decision communicated to the City and the relevant applicant
1. City receives Development Application (DA)
2. Consultation and referrals
3. Assessment
4. Responsible Authority Report (RAR)
Planning Officer prepares Responsible Authority Report (RAR), and RAR is submitted to Development Assessment Panel (DAP) for determination.
Note: If applicable, the RAR may be presented to a Council Meeting or Special Council Meeting if required for comment prior to being submitted JDAP.
5. DAP Meeting and DA determination