Alfred Road, Swanbourne - Road Resurfacing and associated works

Share Alfred Road, Swanbourne - Road Resurfacing and associated works on Facebook Share Alfred Road, Swanbourne - Road Resurfacing and associated works on Twitter Share Alfred Road, Swanbourne - Road Resurfacing and associated works on Linkedin Email Alfred Road, Swanbourne - Road Resurfacing and associated works link

This project is completed.


Roads 2000 will be carrying out road resurfacing and associated works on behalf of the City of Nedlands.

The works will commence on Alfred Road, Swanbourne on Monday 8 June 2020 and will include:

  • Kerb removal & reinstatement;
  • Excavation and road-base works;
  • Road profiling;
  • New asphalt base course;
  • New asphalt wearing course.

The works should be completed within a two-week timeframe however, this is dependent on the weather and resources.

Stage 1 Dayworks: 8–12 June 2020 between the hours of 7am to 5pm

The kerb removal and reinstatement works will be undertaken.

Lane closures will be implemented during the Dayworks utilising stop and slow boards. Local traffic will continue to have access and on-site traffic controllers will be happy to assist.

Stage 2 Night Works: 15–19 June 2020 between the hours of 7pm to 6am

The pavement and resurfacing works will be undertaken.

Road closures will be in place during the Night Works with detours around the work site, local access will be limited during the asphalt operations and if returning home at night you may be asked to make alternative parking arrangements for the shift duration.

The Night Works will be undertaken within the conditions of an approved noise management plan and every effort will be made within reason to minimise the impact of these works while completing in a timely fashion.

Please note that some preparatory works will need to be undertaken outside of these dates and may include surveying and paint markings.

You can view documentation related to the works such as site location, noise management plans and traffic management plans in the Document Library.

This page will be updated via Newsfeeds below.


Roads 2000 will be carrying out road resurfacing and associated works on behalf of the City of Nedlands.

The works will commence on Alfred Road, Swanbourne on Monday 8 June 2020 and will include:

  • Kerb removal & reinstatement;
  • Excavation and road-base works;
  • Road profiling;
  • New asphalt base course;
  • New asphalt wearing course.

The works should be completed within a two-week timeframe however, this is dependent on the weather and resources.

Stage 1 Dayworks: 8–12 June 2020 between the hours of 7am to 5pm

The kerb removal and reinstatement works will be undertaken.

Lane closures will be implemented during the Dayworks utilising stop and slow boards. Local traffic will continue to have access and on-site traffic controllers will be happy to assist.

Stage 2 Night Works: 15–19 June 2020 between the hours of 7pm to 6am

The pavement and resurfacing works will be undertaken.

Road closures will be in place during the Night Works with detours around the work site, local access will be limited during the asphalt operations and if returning home at night you may be asked to make alternative parking arrangements for the shift duration.

The Night Works will be undertaken within the conditions of an approved noise management plan and every effort will be made within reason to minimise the impact of these works while completing in a timely fashion.

Please note that some preparatory works will need to be undertaken outside of these dates and may include surveying and paint markings.

You can view documentation related to the works such as site location, noise management plans and traffic management plans in the Document Library.

This page will be updated via Newsfeeds below.

This project is completed.

  • Works completed

    Share Works completed on Facebook Share Works completed on Twitter Share Works completed on Linkedin Email Works completed link
    supporting image

    The works on Alfred Road are now complete pending Linemarking by Main Roads.

  • Stage 1 to commence 8 June - DAYWORKS

    Share Stage 1 to commence 8 June - DAYWORKS on Facebook Share Stage 1 to commence 8 June - DAYWORKS on Twitter Share Stage 1 to commence 8 June - DAYWORKS on Linkedin Email Stage 1 to commence 8 June - DAYWORKS link
    supporting image

    As noted above, Stage 1 Dayworks will commence 8 June 2020, with Stage 2 expected to begin 15 June 2020.
    Kerb removal and reinstatement works will be undertaken.
    Lane closures will be implemented during the Dayworks utilising stop and slow boards. Local traffic will continue to have access and on-site traffic controllers will be happy to assist.

    These works will only be carried out between the hours of 7am-5pm.
    For more information regarding site locations, detours and other documentation, head to the document library.