Nedlands (West Hollywood) Underground Power Project Progressing

The underground power project is progressing to schedule. A summary of the current status follows:
- Completion of Loftus Street cable jointing – testing in preparation of commissioning for house changeovers.
- Napier Street completion of drilling both sides of the road.
- Transformer installation on Government Road complete.
The proposed dates for construction and status of completion for each of the zones are as follows:
| Zone | Start Date | Finish Date |
| Zone 1 | 30 April 2018 | completed |
| Zone 2 | 11 July 2018 | 15 October 2018 |
| Zone 3 | 2 October 2018 | 21 January 2019 |