Nedlands (West Hollywood) Underground Power Project Progressing

The underground power project is progressing to schedule. A summary of the current status follows:

  • Completion of Loftus Street cable jointing – testing in preparation of commissioning for house changeovers.
  • Napier Street completion of drilling both sides of the road.
  • Transformer installation on Government Road complete.
18 resident issues reported with 17 closed out and one awaiting further action. All issues have been reported direct to the Contractor (Cable Layers) which reflects the effectiveness of the distribution of the resident project advices.

The proposed dates for construction and status of completion for each of the zones are as follows:

Zone

Start Date

Finish Date

Zone 1

30 April 2018

completed

Zone 2

11 July 2018

15 October 2018

Zone 3

2 October 2018

21 January 2019


Categories: Underground power
Share Nedlands (West Hollywood) Underground Power Project Progressing on Facebook Share Nedlands (West Hollywood) Underground Power Project Progressing on Twitter Share Nedlands (West Hollywood) Underground Power Project Progressing on Linkedin Email Nedlands (West Hollywood) Underground Power Project Progressing link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>