How are we progressing?

Western Power's contractors, Cable Layers are nearly half way through the installation of placing power underground in the Hollywood West area.

The proposed dates for completion dates for each zone (click on heading above to view map) is as follows:

  • Zone 1: 30 September 2018
  • Zone 2: 30 October 2018
  • Zone 3: 23 January 2019