Alderbury Street - Underground Power - Town of Claremont Proposal
The City at a Special Meeting on 16 August 2016 received a report in relation to a proposal for underground power by the Town of Cambridge which includes properties on the municipal boundary of Alderbury Street, Floreat. This proposal has proceeded to the next stage which is to undertake a community survey. The community survey is the next step in determining whether the installation of underground power proceeds to the next stage.
The Council resolved as follows:
"Council supports Option 1 with the City contributing 2/9ths and the Town of Cambridge be requested to fund the difference/impact. Survey of residents to the same cost at $6,200 per property for both Nedlands and Cambridge residents."
Breakdown of costs between the stakeholders based on the estimate of $12,400
per lot for Alderbury Street residents (Nedlands side) would be:
City of Nedlands | 22.2% | $2,753 |
Alderbury St residents (Nedlands) | 50.0% | $6,200 |
Western Power | 10.0% | $1,240 |
Town Of Cambridge | 17.8% | $2,207 |
Total | 100.0% | $12,400 |
For further information please refer to the Council minutes (Item No. 7), dated 16 August 2016 (Special Meeting) for a detailed report on the matter.
The Department of Finance have advised the City that the survey for the State Underground Power Program will be completed on Friday, 30 September 2016.
Share Alderbury Street - Underground Power - Town of Claremont Proposal on Facebook
Share Alderbury Street - Underground Power - Town of Claremont Proposal on Twitter
Share Alderbury Street - Underground Power - Town of Claremont Proposal on Linkedin
Email Alderbury Street - Underground Power - Town of Claremont Proposal link
Consultation has concluded