May 2018 → February 2019

Project commencement for West Hollywood area

Includes the installation of the remaining transformers and switch-gear, all new underground network cables along the road reserves, customer mains from the property boundary to the meter board (where required), and new LED street lighting.
November → December 2017

Hollywood Area Underground Power Project - Stage 1 Network Capacity Upgrade - High Voltage Network

13 June → 03 July 2017

Resident Survey

04 July → 28 July 2017

Presentation of survey results to the Council

03 April → 28 April 2017

Council approval process

17 February 2017

Cape Utilities - Work Commences - HV Upgrade - Selby Street to Shenton Park Sub Station

14 February → 31 March 2017

Analysis of survey results, final design and costings, funding models developed

25 January → 13 February 2017

Survey of Hollywood Area Residents being undertaken

14 November 2016

Western Power to commence upgrade of HV underground power cables

26 April 2016

Council resolves to submit application

29 April 2016

Application for underground power to remaining residents submitted

16 August 2016

Western Power to advise on success of being a short-listed application

Once confirmed, further dates will be advised.