Taylor Road (Between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works
The City has subcontracted the company Roads2000 to undertake road resurfacing and associated works on the section of Taylor Road from Stirling Highway to Princess Road, on Monday, 30 January 2017 for a period of up to five weeks, during the hours of 7.00 am and 5.00 pm, Monday to Friday.
The work is being undertaken as a result of the road suffering substantial fatigue cracking and will include upgrades of kerbing, drainage lids, pram ramps and crossovers.
The timetable is as follows:
- Drainage improvements: 30 January to 6 February 2017
- Kerb removal: 6-8 February 2017
- Road surface preparation: 9-10 February 2017
- Spray sealing works: 13 February 2017
- Installation of new kerbs: 15-16 February 2017
- Concreting: 16 February 2017
- Backfilling works: 17-21 February 2017
- Ashphalt works: 22 February 2017
- Completion: 23 February 2017
During this time, road closures will be in place with detours around the work site. Local traffic will continue to have access whilst closures are in place, with on-site traffic controllers assisting motorists and pedestrians.
There will be periods of time (approximately 4 hours) following the laying of new asphalt road surface where access to properties may be limited due to the drying time of the bitumen. In addition, parking on the road will be required whilst the crossover aprons are being installed to each property.
Properties with reticulation may have their reticulation temporarily re-routed during the construction period. The City will repair any damaged reticulation in the verge, however property owners need to ensure that the reticulation system is tested and any faults are reported to the City within two weeks of the works being completed. After this period the City cannot be held responsible for repairs.
For further information or enquiries, please contact the Engineering Projects Coordinator, Paul Beasley, by telephoning the City on (08) 9273 3500.
Thank you for your patience during this time.
Please see the News and Notices Page for all City updates.