Taylor Road (between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works

CLOSED: This discussion has concluded.

Roads2000 have been contracted to undertake road resurfacing and associated works in Taylor Road for a five week period commencing on 23 January 2017. These works will be undertaken during weekdays between the hours of 7.00 am to 5.00 pm.

Road closures will be required with detours in place. These closures will cease at approximately 4.30 pm each day to minimise inconvenience, however we do ask that residents consider increasing their commuting times during peak periods.

Access to your property will be available at all times, however there may be short periods when access cannot be permitted. On these occasions, the City will ensure that contact has been made with you and suitable alternative arrangements have been agreed.

The kerbing will also be replaced and upgraded and where necessary the reticulation will be temporarily rerouted to allow the works to proceed. If the reticulation on your property is damaged during this process, the City will make good the repair. However it is important that the reticulation system be tested and any faults be reported to the City within two weeks of the works being completed. After this period the City cannot be held responsible for repairs.

The works will include:

Drainage

23 to 31 January 2017

Kerb removal

31 January to 2 February 2017

Profiling works

6 February 2017

Asphalt corrector

7 February 2017

Spray sealing

8 February 2017

Kerb installation

10 February 2017

Concreting

13 to 14 February 2017

Brick paving

3 February 2017

Backfilling

15 to 17 February 2017

Asphalting

20 February 2017

City considers that the works to be undertaken will be of mutual benefit for ratepayers, businesses and road users of the City and cooperation during this time is greatly appreciated.

If you are affected or potentially affected by this project, please contact Paul Beasley, Engineering Projects Coordinator, telephone (08) 9273 3625, or email pbeasley@nedlands.wa.gov.au or contact the Contractors, Roads2000 on (08) 9202 0800 or projects3@roads2000.com.au.


Share Taylor Road (between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Facebook Share Taylor Road (between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Twitter Share Taylor Road (between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works on Linkedin Email Taylor Road (between Stirling Highway and Princess Road) - Road Resurfacing and Associated Works link

Please see the News and Notices Page for all City updates.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>