Brockway Road Resurfacing Lane Closure
Brockway Road, Mt Claremont will be having some lane closures as part of the road rehabilitation that the City has commenced.
Civcon Civil will be undertaking profiling and resurfacing on the dates shown below:
BROCKWAY ROAD PROFILING AND RESURFACING SCHEDULE | |||||
|
|
Profiling Crew |
Asphalt Crew |
||
Stage |
Location |
Date on site |
Shift Type |
Date on site |
Shift Type |
1 |
Lemnos to John XXIII -Southbound |
29 April 2021 |
Dayshift |
30 April 2021 |
Nightshift |
1 |
Lemnos to John XXIII – Northbound |
29 April 2021 |
Dayshift |
30 April 2021 |
Nightshift |
2 |
John XXIII to Quintilian – Southbound |
14 – 15 April 2021 |
Dayshift |
14 – 15 April 2021 |
Dayshift |
3 |
Quintilian to Alfred – Southbound |
12 – 13 April 2021 |
Dayshift |
12 – 13 April 2021 |
Dayshift |
4 |
Quintilian to John XXIII - Northbound |
27 April 2021 |
Dayshift |
28 April 2021 |
Dayshift |
Diversions will be installed via Lemnos street.
For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.