Further Road Closures
There will be further road closures to facilitate:
Resurfacing:
|
|
Profiling Crew |
Asphalt Crew |
||
Stage |
Direction of Traffic |
Date on site |
Shift Type |
Date on site |
Shift Type |
1 |
Lemnos to John XXIII -Southbound |
6 May 2021 |
Dayshift |
6 May 2021 |
Nightshift |
1 |
Lemnos to John XXIII – Northbound |
6 May 2021 |
Dayshift |
7 May 2021 |
Nightshift |
2 |
John XXIII to Quintilian – Southbound |
10 – 11 May 2021 |
Dayshift |
10 – 11 May 2021 |
Dayshift |
3 |
Quintilian to Alfred – Southbound |
9 April 2021 |
Dayshift |
18 April 2021 |
Dayshift |
4 |
Quintilian to John XXIII - Northbound |
4 – 5 May 2021 |
Dayshift |
4 – 5 May 2021 |
Dayshift |
Dual Path Construction:
Profiling Crew |
Asphalt Crew |
||||
Stage | Direction of Traffic | Date on site | Shift Type | Date on site | Shift Type |
N/A | Southbound | N/A | N/A | 4 May 2021 | Dayshift |
Check out the document library for more info.
For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.
Consultation has concluded