Delays due to weather

The resurfacing and dual path construction works have been delayed due to weather.

See updated schedule below:

Resurfacing:

Profiling Crew

Asphalt Crew

Stage

Direction of Traffic

Date on site

Shift Type

Date on site

Shift Type

1

Lemnos to John XXIII -Southbound

6 May 2021
(COMPLETED)

Dayshift

13 May 2021
7pm - 5am

Nightshift

1

Lemnos to John XXIII – Northbound

6 May 2021
(COMPLETED)

Dayshift

14 May 2021
7pm - 5am

Nightshift

2

John XXIII to Quintilian – Southbound

7 & 10 May 2021
(COMPLETED)

Dayshift

17 & 18 May 2021
9am - 7pm

Dayshift

3

Quintilian to Alfred – Southbound

9 April 2021
(COMPLETED)

Dayshift

12 April 2021
(COMPLETED)

Dayshift

4

Quintilian to John XXIII - Northbound

4 5 May 2021
(COMPLETED)

Dayshift

17 & 18 May 2021
7am - 3pm

Dayshift


Dual Path Construction:



Profiling Crew
Asphalt Crew
Stage Direction of Traffic Date on site Shift Type Date on site
Shift Type
N/A Southbound N/A N/A 4 May 2021
(COMPLETED)
Dayshift


Check out the document library for the latest closure maps.

The working times have been adjusted to allow for an improved flow during school pickup and drop off times.
See below for works breakdown:

NORTHBOUND LANE CLOSURES:

  • Works allowed between 7am - 3pm
  • Night works between 7pm - 5am

SOUTHBOUND LANE CLOSURES

  • Works allowed between 9am - 7pm
  • Night works between 7pm - 5am

For works on 17 & 18 May, only one lane on Brockway will be closed at any one time.

For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.

Share Delays due to weather on Facebook Share Delays due to weather on Twitter Share Delays due to weather on Linkedin Email Delays due to weather link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>