2021 Brockway Road - Shared Pathway and Brockway Road Rehabilitation

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

The City of Nedlands is about to commence two significant capital works projects on Brockway Road, Mt Claremont from March 2021. They are the Brockway Shared Pathway and Brockway Road Rehabilitation road upgrade. Civcon have been awarded the contract to undertake this work. Below is the information relating to both projects to ensure you can plan your travel in advance to avoid delays.

Brockway Road - Shared Pathway

The City of Nedlands has been awarded funding by the Department of Transport to assist with the development of a Pedestrian Shared Pathway on Brockway Road, Mt Claremont from Underwood Avenue to Quintilian Road.

Stage 1

16 March - late May 2021 - Underwood Avenue to Lemnos Street

Construction of a 2.5m wide dual use path within the south bound verge on Brockway Road. A 40kph speed limit will be in place during this time.

Brockway Road Rehabilitation and Road Resurfacing

The City is planning major road resurfacing works for Brockway Road, between Alfred and Lemnos Road, Mt Claremont from the 22 March - 4 May 2021. Updates relating to possible road closures or detours will be provided on this project page, so we encourage the community to stay informed on the various detours to be put in place to ensure minimal disruption. Main Roads is partnering with the City of Nedlands by partially funding this project.

Stage 2

22 March - late May 2021 - Alfred Road and Lemnos Street, Mt Claremont

Updates relating to possible road closures or detours will be provided on this project page, so we encourage the community to stay informed on the various detours to be put in place to ensure minimal disruption.

Main Roads is partnering with the City of Nedlands by partially funding this project.

How can you get involved, find out more or provide feedback?

  • Reviewing the various documents relating to each of these projects, please visit the document library
  • Asking us a question using the Ask us a Question tab and we will respond.
  • Updates on the two projects will occur in an Updates tab on this engagement page.

To participate in other community engagement projects, please register, by clicking on the 'Register to get involved' tab at the top of this page.

The City of Nedlands is about to commence two significant capital works projects on Brockway Road, Mt Claremont from March 2021. They are the Brockway Shared Pathway and Brockway Road Rehabilitation road upgrade. Civcon have been awarded the contract to undertake this work. Below is the information relating to both projects to ensure you can plan your travel in advance to avoid delays.

Brockway Road - Shared Pathway

The City of Nedlands has been awarded funding by the Department of Transport to assist with the development of a Pedestrian Shared Pathway on Brockway Road, Mt Claremont from Underwood Avenue to Quintilian Road.

Stage 1

16 March - late May 2021 - Underwood Avenue to Lemnos Street

Construction of a 2.5m wide dual use path within the south bound verge on Brockway Road. A 40kph speed limit will be in place during this time.

Brockway Road Rehabilitation and Road Resurfacing

The City is planning major road resurfacing works for Brockway Road, between Alfred and Lemnos Road, Mt Claremont from the 22 March - 4 May 2021. Updates relating to possible road closures or detours will be provided on this project page, so we encourage the community to stay informed on the various detours to be put in place to ensure minimal disruption. Main Roads is partnering with the City of Nedlands by partially funding this project.

Stage 2

22 March - late May 2021 - Alfred Road and Lemnos Street, Mt Claremont

Updates relating to possible road closures or detours will be provided on this project page, so we encourage the community to stay informed on the various detours to be put in place to ensure minimal disruption.

Main Roads is partnering with the City of Nedlands by partially funding this project.

How can you get involved, find out more or provide feedback?

  • Reviewing the various documents relating to each of these projects, please visit the document library
  • Asking us a question using the Ask us a Question tab and we will respond.
  • Updates on the two projects will occur in an Updates tab on this engagement page.

To participate in other community engagement projects, please register, by clicking on the 'Register to get involved' tab at the top of this page.

Consultation has concluded
  • Delays due to weather

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The resurfacing and dual path construction works have been delayed due to weather.

    See updated schedule below:

    Resurfacing:

    Profiling Crew

    Asphalt Crew

    Stage

    Direction of Traffic

    Date on site

    Shift Type

    Date on site

    Shift Type

    1

    Lemnos to John XXIII -Southbound

    6 May 2021
    (COMPLETED)

    Dayshift

    13 May 2021
    7pm - 5am

    Nightshift

    1

    Lemnos to John XXIII – Northbound

    6 May 2021
    (COMPLETED)

    Dayshift

    14 May 2021
    7pm - 5am

    Nightshift

    2

    John XXIII to Quintilian – Southbound

    7 & 10 May 2021
    (COMPLETED)

    Dayshift

    17 & 18 May 2021
    9am - 7pm

    Dayshift

    3

    Quintilian to Alfred – Southbound

    9 April 2021
    (COMPLETED)

    Dayshift

    12 April 2021
    (COMPLETED)

    Dayshift

    4

    Quintilian to John XXIII - Northbound

    4 5 May 2021
    (COMPLETED)

    Dayshift

    17 & 18 May 2021
    7am - 3pm

    Dayshift


    Dual Path Construction:



    Profiling Crew
    Asphalt Crew
    Stage Direction of Traffic Date on site Shift Type Date on site
    Shift Type
    N/A Southbound N/A N/A 4 May 2021
    (COMPLETED)
    Dayshift


    Check out the document library for the latest closure maps.

    The working times have been adjusted to allow for an improved flow during school pickup and drop off times.
    See below for works breakdown:

    NORTHBOUND LANE CLOSURES:

    • Works allowed between 7am - 3pm
    • Night works between 7pm - 5am

    SOUTHBOUND LANE CLOSURES

    • Works allowed between 9am - 7pm
    • Night works between 7pm - 5am

    For works on 17 & 18 May, only one lane on Brockway will be closed at any one time.

    For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.

  • Asphalting Brockway Pedestrian Path

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Civcon are due to start asphalting the Brockway Pedestrian Path on Friday 30 April 2021, weather permitting.

    The works are planned over the next few weeks and is dependent on weather conditions and asphalt availability.

    The carpark next to the UWA Nedlands football club will be used as a laydown area from 7am – 5pm and speed in the area will be slowed down to 40km/hr (between Lemnos and Underwood).

    Traffic management will be set up for pedestrian and cars to manage movement on the road and in the parking area.

    Further updates will be posted on this page.

  • Further Road Closures

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: This schedule has been updated.

    There will be further road closures to facilitate:

    Resurfacing:

    Profiling Crew

    Asphalt Crew

    Stage

    Direction of Traffic

    Date on site

    Shift Type

    Date on site

    Shift Type

    1

    Lemnos to John XXIII -Southbound

    6 May 2021

    Dayshift

    6 May 2021

    Nightshift

    1

    Lemnos to John XXIII – Northbound

    6 May 2021

    Dayshift

    7 May 2021

    Nightshift

    2

    John XXIII to Quintilian – Southbound

    10 – 11 May 2021

    Dayshift

    10 – 11 May 2021

    Dayshift

    3

    Quintilian to Alfred – Southbound

    9 April 2021
    (Completed)

    Dayshift

    18 April 2021
    (Completed)

    Dayshift

    4

    Quintilian to John XXIII - Northbound

    4 5 May 2021

    Dayshift

    4 5 May 2021

    Dayshift


    Dual Path Construction:



    Profiling Crew
    Asphalt Crew
    Stage Direction of Traffic Date on site Shift Type Date on site
    Shift Type
    N/A Southbound N/A N/A 4 May 2021 Dayshift


    Check out the document library for more info.

    For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.

  • Brockway Road Resurfacing Works - Sunday 18 April 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: These works have been completed.

    Brockway Road will be partially closed for resurfacing between Alfred Rd and Quintilian Road on Sunday 18 April between the hours of 7am and 5pm.

    One lane either North Bound or South Bound will remain open at all times.
    Road closure signs and diversion routes will be installed.

    Site Contact: Mick Kelly 0438 727 917

  • Brockway Road Resurfacing Lane Closure

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: This work schedule has been updated above.
    supporting image


    Brockway Road, Mt Claremont will be having some lane closures as part of the road rehabilitation that the City has commenced.

    Civcon Civil will be undertaking profiling and resurfacing on the dates shown below:



    BROCKWAY ROAD PROFILING AND RESURFACING SCHEDULE

    Profiling Crew

    Asphalt Crew

    Stage

    Location

    Date on site

    Shift Type

    Date on site

    Shift Type

    1

    Lemnos to John XXIII -Southbound

    29 April 2021

    Dayshift

    30 April 2021

    Nightshift

    1

    Lemnos to John XXIII – Northbound

    29 April 2021

    Dayshift

    30 April 2021

    Nightshift

    2

    John XXIII to Quintilian – Southbound

    14 – 15 April 2021

    Dayshift

    14 – 15 April 2021

    Dayshift

    3

    Quintilian to Alfred – Southbound

    12 – 13 April 2021

    Dayshift

    12 – 13 April 2021

    Dayshift

    4

    Quintilian to John XXIII - Northbound

    27 April 2021

    Dayshift

    28 April 2021

    Dayshift


    Diversions will be installed via Lemnos street.

    For further information regarding the diversion route or access to your property contact Civcon Civil Project Manager Shane Stephens 0428 399963.