12 November 2018 → 31 January 2019

Construction of toilet facilities

01 February 2018

Phase 2 Commencement

It is planned to undertake the construction of the toilet block, the perimeter cycle track and undertake landscaping of the surround area
18 January → 24 February 2017

Enabling Works

Relocation of the sewerage pump station and power supply to the site
27 February → 30 June 2017

Play Space Construction

The majority of the play space will be constructed during this period.
03 July → 27 October 2017

Other Construction

The remaining construction works will be completed including the perimeter fence. Coinciding will be the second stage of the restoration of the river wall (proposed September 2017 to February 2018)